Progress Report
May 29-Jun 4 , 2005 // CONSTRUCTION LOG #34
Pictures: none (curbs are not very exciting).
NEW CONSTRUCTION
Permit: The soil study was submitted to SENTENA on
Monday. It was a generic report on soil conditions,
geological profile and known aquifers. This project
was deemed to NOT represent a threat to ground water
contamination. This report is the last known
requirement. We wait.
Curbs and garden night lighting continued this week.
Most of the night lighting is now done; the remaining
will be done later after the construction is finished.
Misc: The wrought iron and ceramic table tops I had
made are finally done but didn't end up being the
bargain I thought they were going to be. The wall unit in 113 is also completed; it turned
out nice.
The food preparation counter and bar-b-q area in the
large rancho is nearly finished. I have a hunt on for
a 7' pool table. It's early yet but if I run across
one, I'll probably get it. I'm going to have some
roll down curtains in the large rancho to protect from
wind blown rain and from wind as I expect to have a
ping pong table there as well.
Unit 107: The sub roof is almost fully installed.
Rough-in wiring is proceeding as is interior and
exterior boarding. It's beginning to look like a
house. We enlarged the master bedroom and redesigned
the master bathroom by encroaching into a small,
rather non-functional area at the top of the stairs.
This is going to be a very nice house; It has a
fantastic unobstructed view of the large pool and the
mountains behind as well as a west facing balcony for
sunsets. On the ground floor, the back terrace can be
accessed and seen from two different places. We are
finding places to put storage cabinets and
eventually, eye candy.
VOIP (internet phone): it is now working like a dream. We have added one other household to the line and we now have it wired such that it is very convenient. Calls are clear and there is no time delay -it's just like a normal phone call; distance is not an issue. In fact, the quality is better than many times when I phoned CR from Canada. For callers from the 315 area code in the U.S. and from the 416 area code in Canada, calls are considered local. Outside those areas, I believe the cost is to call that area code even though it rings in Costa Rica. A friend and his wife stayed with us on Monday. He brought us our mail-no disasters in the mail this time. They hopped a bus to their home in Ciudad Neilly near the border with Panama -a long ways and hot when you get there but they like it...
OUR LIVES
Lita cooked up a pot of curried lentils and whatever
and made a party around the pool last weekend. We ate
leftovers into mid week -it's amazing how far $4 can
be stretched. She also cooked a wonderful pasta and
organized a dinner Thursday evening for a friend who
had fallen and hurt herself.
I was taken to see the new house of my maestro de obra
(site foreman). Through his work here and a loan we
gave him, he was able to buy a fixer-upper. It's a
nice little three bedroom home and much better than
the one he moved from. We had some kitchen cabinets
which we had pulled from 107 that I gave him and some
bathroom fixtures which we no longer needed. It's
nice to see that you've helped some one improve their
life.
We played pool one evening with a resident and his two
young children. They were great and better than Lita
and I (which isn't much of a challenge). I think
their professor parents are teaching them to be pool
sharks so they can supplement the cost of their
university education.
Last night it was a Gino's pizza birthday party for
Susan. Since Gino's is next to the church, he can't
get a liquor license so we bring our own. As always,
great pizza-we made several new converts to tuna
pizza.
And that's it for this week.Kinda quiet but useful
work getting done.
Brian, Lita, Hugo and Vicka -the pigeon toed
parrot